This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.
117 MW Abril
The “Akin Solar” Project consists of the construction and commissioning of a solar panel park with a capacity of 130 MW (the Project), on a approximately 266 hectares with a 7 km length and 230 kV transmission line to the Puerto Libertad Substation.
Jema provided a turnkey solution to maximise the reliability and correct operation of the equipment. A total of 44 IFX6 3-column, bi-directional solar inverters were supplied and distributed across the 266 hectares of the solar plant.
Supply:
- 22 SI 5340 MW Power conversion 1500 V